ClientHUD Office of Healthcare Programs (OHP)
Delivered byCapital-Hascon JV, prime contractor
Contract value$3.4M (base year plus four option years)
PeriodSeptember 2025 – present
ReachOn-site audits in 30+ states
Joint venture

HUD Technical Suitability of Products (TSP) Program

HUD's TSP program decides whether building materials, products and systems that aren't already covered by recognized standards can be used in HUD-insured housing and healthcare facilities. Capital-Hascon won the contract to support the program on behalf of HUD's Office of Healthcare Programs. We review sponsor submittals, keep HUD's library of acceptance documents current, and audit the manufacturers and administrators who hold approvals. All of this work follows HUD Handbook 4950.1 Rev. 3.

As prime contractor, Capital-Hascon carries full responsibility for program management, technical review, audits and deliverable quality, and self-performs the work. Our teams carry out on-site inspections and audits of product sponsors, manufacturers and administrators in more than 30 states. They produce written reports with inspection checklists to HUD deadlines, resolve the COR's comments and report monthly.

A dedicated Project Manager leads the work, and a licensed Architect or Professional Engineer with more than 20 years of building-systems experience provides technical authority. Every deliverable passes a two-tier QA review covering technical validation and editorial checks, and is measured against the Acceptable Quality Levels (AQLs) in HUD's Quality Assurance Surveillance Plan.

On-site inspection & auditTechnical reviewHUD-insured housingPrime contract
5.1

Transition

A 60-day transition-in with a catalogued inventory of MR, SEB, MEB and AL files, plus a transition-out plan delivered within 90 days of award.

5.2

Program management

The project management plan, monthly status meetings and activity reports, the sponsor contact master list and standardized procedures.

5.3

New acceptance reviews

Completeness checks within 10 business days and P.E.-led technical reviews within 35 for new MR, SEB, MEB, UM and SLA submittals.

5.4

Bulletin revisions

Technical and editorial revisions to existing Materials Releases, Engineering Bulletins and Use of Materials Bulletins.

5.5

Renewals

A calendar of renewals that flags each bulletin 120 days before it expires, followed by renewal notices to sponsors.

5.6

Audits

Onsite and virtual audits of manufacturers, UM administrators and Category III state programs.

5.7

UM administrator review

Rubric-based evaluation of organizations applying to become Use of Materials Administrators.

5.8

Program documents

Revisions to HUD Handbook 4950.1 (Rev. 4) and Handbook 4910.1, the TSP SOP, the Minimum Property Standards and bulletin templates.

Hascon · Multifamily construction

Construction management, inspection and quality oversight

Hascon, a Capital-Hascon member, provided complete construction management, inspection and quality oversight on four multifamily projects in Maryland, totaling 775 units and beds. Hascon performed 100% of the work on each project.

  • Inspected and verified work in place against the approved contract documents, permits and owner quality standards
  • Ran the quality assurance program, documenting deficiencies and tracking corrective actions to closure
  • Reviewed and approved the contractor's monthly payment requests
  • Coordinated with county permit and inspection offices through occupancy and close-out
Potomac, MD

Park Potomac Condominium, Building 1 (South Tower)

Client
Foulger-Pratt Development
Units
90 units, 10 stories
Value
$52M
Duration
24 months

Coordinated design, permitting and bidding before construction, then managed construction, inspection and quality oversight through occupancy.

Potomac, MD

Park Potomac Condominium, Building 2 (North Tower)

Client
Foulger-Pratt Development
Units
94 units, 10 stories
Value
$54M
Duration
24 months

Covered building systems, dwelling units, common areas, amenities, parking, site improvements and utility connections, from pre-construction through close-out.

Silver Spring, MD

Citron Apartment Community

Client
Foulger-Pratt Development
Units
222 units
Value
$70M+
Duration
36 months

Pre-construction coordination, construction-phase inspection and quality oversight, payment-request review and occupancy readiness for a 222-unit rental community.

College Park, MD

The Enclave Student Housing, University of Maryland

Client
Star Global Ventures
Units
369 beds/units
Duration
24 months

Construction management, inspection and quality oversight for the student housing developer, working with WSP/Louis Berger as the developer's project manager.

ClientU.S. Naval Academy
LocationPatuxent River, MD
Value$6.94M final
Period2017 – 2020
Hascon

Hangar H111 Life Extension, Phase 3

Demolition and complete renovation of the administrative wing of Hangar H111, an approximately 15,000-square-foot office facility. The team managed the project from award to close-out and coordinated scope growth from the $5.38M award to the $6.94M final contract value.

RenovationConstruction managementDoD
ClientU.S. Naval Academy
LocationAnnapolis, MD
Value$8.6M final
Period2009 – 2012
Hascon

Child Development Center

Design-build delivery of a 22,000-square-foot Child Development Center, including a complete renovation of the HVAC system. The project combined design management, A&E coordination and construction under a single contract.

Design-buildHVACInstitutional
ClientNAVFAC
LocationPatuxent River, MD
Value$2.3M final
Period2012 – 2014
Hascon

Building 4 HVAC Replacement

Complete replacement of the building's HVAC systems, including demolition and associated repairs. The work was sequenced so the occupied facility could keep operating.

MechanicalRenovationDoD
ClientNational Cancer Institute
LocationFort Detrick, MD
Value$2.0M final
Period2014 – 2015
Hascon

Laboratory Building 469 Renovation

Interior renovation of a research laboratory, covering demolition, flooring, plumbing, HVAC and electrical work, carried out to the strict standards of an active federal research campus.

LaboratoryMEPNIH
ClientNAVFAC
LocationPatuxent River, MD
Value$367K
Period2011 – 2012
Hascon

Building 2805 Chiller Replacement

Complete replacement of the existing chiller system and associated repairs for a building of more than 500,000 square feet, delivered at the original award value with no cost growth.

MechanicalOn budgetDoD
ClientPE-backed healthcare services company
Scope250+ locations, 24 states
AIA Capital Group

Multi-State Operations Transformation

Directed a transformation initiative across a national footprint and served as interim procurement lead. The work covered stakeholder alignment, sourcing strategy with OEMs and distributors, and executive onboarding. It improved operational efficiency and cash flow.

Program managementProcurementHealthcare
ClientFortune 200 global retailer
ScopeMulti-brand supply chain
AIA Capital Group

Supply Chain Visibility Program

Built detailed process maps and an executive dashboard to track performance across brands and cost centers. Structured leadership updates improved cross-functional collaboration and the response to logistics challenges.

Executive reportingProcess designRetail
Key personnel experience

Large-scale programs led by our partners

Before the joint venture, our principals held leadership roles on some of the largest public programs in the country.

$3.0B

USPS National Deployment

Program management services for the deployment of up to 250 mail processing and distribution facilities nationwide.

$1.25B

DOE Superconducting Super Collider

Design and construction program management covering more than 54 miles of tunnels, along with highways, bridges, utilities and research facilities.

$110M+

GSA U.S. Courthouse, Minneapolis

A 15-story, 500,000-gross-square-foot design-build federal building and courthouse, recognized with a GSA award.

250K SF

Pentagon Remote Delivery Facility

Design and construction management of a secure, blast-resistant screening facility for all Pentagon shipments.

$550M

Downtown Silver Spring P3

A public-private redevelopment with a 160-unit multifamily building, a hotel, office and retail space. It received a Best Honor Award from Montgomery County.

$600M

Park Potomac

A mixed-use community with six high-rise condominium and apartment buildings totaling 450 units, plus office and retail space.

Need past-performance references?

We provide client references to contracting officers and teaming partners on request.

Request references